Forecast at completion
The higher of budget and committed amount plus approved changes. It moves the moment a change order is approved, not when it is paid.
Home · Free tool
Budget, committed contracts, approved change orders and payments in one table. You see the forecast at completion, the variance per line and how much of your contingency is already used.
Your numbers stay in this browser. Nothing is sent to us.
The higher of budget and committed amount plus approved changes. It moves the moment a change order is approved, not when it is paid.
Budget minus forecast. Red means the line will end over budget unless something changes.
Approved changes as a share of your contingency. Past half of it before the roof is on, it is time to review scope.