Home · Sample: Contract Scope and Payment Review
Exactly what you receive after payment.
Sample report. A fictitious one-page contract we wrote for this demonstration. Names and numbers are invented. This is the unedited output of the report engine.
Overall: RED. The contract is a one-page document with a price, a deposit and a payment method, but no scope by trade, no specifications, no allowances, no exclusions and no schedule. The 30 percent deposit is large for a contract with no defined work behind it. This is a document review only, not an inspection, not an engineering opinion and not legal advice. Legal terms were not reviewed. Have the contract reviewed by a Florida licensed attorney before signing.
REDScope of work: The contract says only "new single family residence, 3,800 sq ft." There is no trade-by-trade description (site work, foundation, framing, roofing, windows and doors, MEP, insulation, drywall, flooring, cabinets, tile, paint, landscaping). The $1,450,000 price therefore does not buy a defined product.
REDPlans and specifications: No plans, drawings, spec sheets or finish schedule are referenced. Quantities and quality levels are not defined, so any upgrade or substitution is open to dispute.
REDAllowances: None are listed. Cabinets, countertops, flooring, plumbing and lighting fixtures, appliances and landscaping are usually allowance items, and none are priced. I cannot judge whether allowances are realistic because none exist. Either everything is included at an unstated quality level, or allowances will appear later.
REDExclusions: None are stated. Common items that are often excluded include permit and impact fees, survey and soil testing, utility connections, pool, fencing, driveway, landscaping and irrigation, and appliances. Without a list, nobody can tell what is in the price.
REDSchedule: "Start work when convenient after permits are issued" gives no start date, duration, milestones or completion date. There is nothing to measure progress against.
REDPayment versus progress: The deposit of $435,000 (30 percent of $1,450,000) is due at signing, before any work. The remaining $1,015,000 is paid in monthly draws "as invoiced," with no schedule of values and no link to completed work, inspections or stored materials. In economic terms this is front-loaded and not progress-based.
YELLOWPrice per square foot: $1,450,000 divided by 3,800 sq ft is about $382 per sq ft. I cannot say whether this is reasonable. No benchmark data was provided, and the price depends on finish level, site conditions and flood requirements, none of which are defined.
REDPrice certainty: The contractor may adjust the price for material cost increases "at its discretion," with no cap, index or documentation requirement. From a cost-control view the $1,450,000 is not a firm number. Whether this term is acceptable is a question for a Florida licensed attorney.
YELLOWSite and flood conditions: No flood zone, elevation or site information was provided, and no flood lookup was included. Foundation and elevation costs may materially affect the price and scope.
YELLOWPermits and design: The contract does not say who obtains the permits, who pays for them, or whether design documents exist. The contractor starts "after permits are issued," so permit responsibility affects both cost and timing.
1. Full plans and a specification book.
2. A trade-by-trade scope and a schedule of values (price broken down by trade or phase).
3. A finish schedule listing brand, model, grade and color.
4. An allowance schedule with amounts.
5. A written exclusions list.
6. A start date, a duration or completion date, and milestone dates.
7. A draw schedule tied to completed milestones, with inspection sign-off before payment.
8. Permit responsibility, site conditions and flood zone information.
9. A basis for the price (cost estimate or per-trade quotes).
No FACTS were supplied with this order, so this report relies only on the contract and your answers, and no [us-xxx] references are cited.
1. Please provide the plans, specification book and finish schedule that this price is based on.
2. Please provide a line-item breakdown by trade that adds up to $1,450,000.
3. Which items are allowances, and at what dollar amounts?
4. What is excluded from the price (permits, impact fees, utilities, landscaping, pool, appliances, survey and soil testing)?
5. What are the start date, milestone dates and substantial completion date?
6. Why is a 30 percent deposit required, and what does it cover? Can it be reduced to a smaller amount?
7. Can draws be tied to completed milestones with inspection approval, instead of monthly invoices?
8. Who applies for and pays for permits, and what is the flood zone and required finished floor elevation?
9. Can material cost increases be capped, documented and approved by me in writing before they are charged?
1. Do not sign or pay the deposit until items 1 to 9 above are provided in writing.
2. Have the contractor attach plans, specs, allowances, exclusions, schedule and a milestone-based draw schedule to the contract.
3. Request two comparison bids or an independent cost estimate on the same plans to test the $382 per sq ft figure.
4. Look up the property's flood zone and ask the contractor to confirm its effect on the foundation and price.
5. Have a Florida licensed attorney review the contract, including the price adjustment, warranty and dispute terms, which I did not review.
Legal terms were not reviewed. Have the contract reviewed by a Florida licensed attorney before signing.