Sample report. Real public data for a well-known public address on Ocean Drive, Miami Beach, with example numbers for cost and value. This is the unedited output of the report engine.
Overall: RED. The address is in FEMA Zone AE with a base flood elevation of 8 ft [fema-lookup]. Your numbers put the renovation at 60 percent of value, above the 50 percent substantial improvement line [us-011]. This is a document review only, not an inspection, engineering opinion or legal advice. If the numbers hold, the whole building likely must meet current flood rules, with a lowest floor at 9 ft or higher [us-010].
REDFlood zone. The FEMA lookup matched your address to Zone AE on FIRM panel 12086C, a Special Flood Hazard Area, with a BFE of 8 ft [fema-lookup]. An SFHA is the area with a 1 percent annual chance of flooding [us-009]. The lookup does not state the elevation datum. Confirm it on the FIRM or an elevation certificate.
REDLowest floor elevation. The Florida Building Code requires the lowest floor at or above BFE plus 1 foot, or the design flood elevation, whichever is higher [us-010]. From the lookup that is 8 + 1 = 9 ft, as a minimum. The local design flood elevation could be higher, and I have no data on it. If the lot is a Coastal A Zone, the rule shifts to the bottom of the lowest horizontal structural member [us-010]. The lookup does not say which applies.
RED50 percent rule. Your cost of $600,000 against a value of $1,000,000 is 60 percent [owner answers]. Substantial improvement means work costing 50 percent or more of the structure's market value before work starts [us-011]. If that holds, the building would need to be brought up to current flood requirements, which usually means raising or reworking the lowest floor to 9 ft or higher. Two things could change this. The value must be the structure's market value, and your $1,000,000 may include land, which would push the percentage higher. Also, the cost must be the full cost of the work, so a lower or higher final estimate changes the result. Excluded work is limited to minimum corrections of code violations identified by the building official, and alterations of a historic structure that do not preclude its historic designation [us-011].
YELLOWExisting floor elevation unknown. No documents were attached, so I cannot compare your current lowest floor to 9 ft. Without an elevation certificate, the size of the gap and the cost to close it are unknown.
YELLOWNFIP limits. An NFIP homeowner building policy pays up to $250,000 and contents up to $100,000 [us-012]. Commercial policies pay up to $500,000 each for building and contents [us-012]. Against a $1,000,000 value, an NFIP policy leaves a large gap, even if part of that value is land. Your property type (single family, condo, commercial) is not stated, and it determines which limit applies.
YELLOWCCCL. The lookup returned nothing on the Coastal Construction Control Line. The lot is on the oceanfront side of Miami Beach, so check it. If the lot is within CCCL jurisdiction, special siting and design criteria apply, and they can be stricter than the rest of the coastal building zone [us-013]. Verify with the Florida DEP CCCL program at 850-245-2094 or CCCL@FloridaDEP.gov [us-013].
YELLOWHVHZ wind design. Miami-Dade and Broward make up the High Velocity Hurricane Zone [us-006]. Miami Beach is in Miami-Dade County, so HVHZ provisions apply to the renovation. Whether the lot also sits in a wind-borne debris region depends on the design wind speed and distance from the water [us-006]. Your designer should confirm this.
YELLOWCode edition timing. The Florida Building Code 9th Edition (2026) takes effect December 31, 2026. Permit applications submitted on or after that date must comply with it [us-002]. The lookup was run 2026-10-06, so your filing date may decide which edition governs. I have no data on how the new edition changes flood or wind rules.
1. An elevation certificate or survey showing the current lowest floor elevation and datum.
2. The structure's market value, separate from land, from an appraisal or the county property appraiser's building value.
3. A detailed contractor estimate for the full scope.
4. Property type and use.
5. Miami Beach's local design flood elevation, if it is higher than BFE plus 1 ft.
6. CCCL status, historic designation status, and whether the lot is a Coastal A Zone.
7. Any existing flood insurance policy.
1. To the City of Miami Beach floodplain manager: What is the design flood elevation for this parcel, and is it above 9 ft? Is the lot a Coastal A Zone?
2. To the building department: How do you calculate market value for the 50 percent test, and which cost items count?
3. To the building department: Is the property in a historic district, and would that exclusion apply to my scope?
4. To Florida DEP: Is this parcel seaward of or within the CCCL?
5. To my contractor and designer: Can the scope be priced and documented in full, and what does raising the floor to 9 ft or higher cost?
6. To my insurance agent: What are my NFIP limits, and is excess flood coverage available for this property?
1. Order an elevation certificate from a Florida licensed surveyor.
2. Get an appraisal or other supported value of the structure alone.
3. Get a full written cost estimate and compare it to that value.
4. Send the questions above and collect the answers in writing.
5. Decide on a permit filing date with the 9th Edition cutoff of December 31, 2026 in mind [us-002].
6. Check coverage with your insurance agent before design is finalized.