Section 553.792(1)(a), Florida Statutes, requires a local government using its own plans reviewer to approve, approve with conditions, or deny a complete and sufficient building permit application within set timeframes unless the applicant waives them in writing. These include 30 business days for residential units, including single-family dwellings, under 7,500 square feet, 60 business days for such structures of 7,500 square feet or more, 60 business days for nonresidential buildings under 25,000 square feet, and 60 business days for multifamily residential not exceeding 50 units. The local government must tell the applicant within 5 business days after receipt what information, if any, is needed to make the application complete, or the application is deemed complete. If the local government misses a deadline, it must reduce the building permit fee by 10 percent for each business day of delay, subject to exceptions such as a written extension, applicant-caused delay, or force majeure. [us-005]
Permit applications for properties in unincorporated Miami-Dade County can be submitted online through the County's permitting portal or in person at the Permitting and Inspection Center, while properties in incorporated cities are permitted by each city's own building official. Plan review can include building, structural, and trade review, zoning, impact fee, and public works review, environmental and flood review, and, where applicable, Water and Sewer, Fire Rescue, or Department of Health review. The upfront fee covers an initial plan review and one follow-up review per discipline, with a rework fee for each additional review. Permit applications expire after 180 days, and a permit can expire if work does not start or an approved inspection does not occur within 180 days, with an available extension of 180 days. Work done without a permit after a Notice of Violation is subject to a double fee of an additional 100% of the usual permit fees. [us-036]
The City of Miami uses an electronic plan review system called ePlan, in which building permit applications are created in the iBuild portal and drawings and documents are uploaded to ProjectDox. A City Permitting Coordinator reviews the application and submittals for acceptance before plan review begins. The City's estimated first review cycle is approximately 14 business days for building permit applications, around 35 business days for special permit applications, and about 40 business days for Utility-Excavation or Non-Construction permit applications. Projects that require Miami-Dade County DERM or Water and Sewer approval, or payment of County impact fees, must also complete the Miami-Dade County Municipal Application, and those County fees are paid separately. [us-037]
Section 553.791(2)(a), Florida Statutes, allows the fee owner of a building, or the fee owner's contractor with explicit written authorization from the owner, to use a private provider for plans review, building code inspection services, or both, and the local jurisdiction must reduce the permit fee by the amount of cost savings realized. A private provider is a person licensed as a building code administrator under part XII of chapter 468, an engineer under chapter 471, or an architect under chapter 481. The owner or contractor must notify the local building official in writing at the time of permit application, or by 2 p.m. local time, 2 business days before the first scheduled inspection. When a private provider performs plans review, the local building official must issue the permit or give written notice of specific code deficiencies within 10 business days after receipt of the application and the provider's affidavit, or the application is deemed approved and the permit must be issued on the next business day. For a certificate of occupancy or certificate of completion, the official must act within 10 business days, or 2 business days for single-family or two-family dwellings, after receiving a complete request with the provider's certificate of compliance. [us-004]
A Miami-Dade County Permitting and Inspection Center notice states that the Florida Building Code Ninth (2026) Edition becomes effective on December 31, 2026. All permit applications and plans submitted on or after that date must comply with the new edition. Any application submitted through the County's online portal after the close of business at 4 PM on December 30, 2026, must comply with the 2026 edition. For expired permit applications filed before December 30, 2026, the County will grant extensions for permit issuance only if the request is made in writing, shows the application was pursued in good faith, and is made no later than 180 days after expiration. [us-002]
Applied to your projectPermit Readiness Report, USD 199 →
General information about Florida rules, compiled from official sources. Not legal advice and not an inspection or engineering opinion; for your own case ask a Florida licensed attorney, engineer or the building department.