How Florida's construction lien process works for homeowners: notice of commencement, notice to owner, final payment affidavit and lien waivers.
Under section 713.13(1)(a), Florida Statutes, an owner or the owner's authorized agent must record a notice of commencement in the clerk's office before actually commencing an improvement, and must post either a certified copy or a notarized statement that it has been filed for recording along with a copy. The owner must sign the notice and no one else may sign in the owner's place. If the improvement is not actually commenced within 90 days after recording, the notice is void. Unless a different date is stated, a notice of commencement is not effective against later conveyances, mortgages, liens, creditors, or purchasers after 1 year from recording, and payments made by the owner after the notice expires are considered improper payments. The statutory form warns that the notice must be recorded and posted on the site before the first inspection. [us-017]
Section 713.06(2)(a), Florida Statutes, requires all lienors under section 713.06, except laborers, to serve a notice on the owner as a prerequisite to perfecting a lien. The notice must give the lienor's name and address, a description of the property, and the nature of the services or materials furnished. It must be served before commencing, or not later than 45 days after commencing, to furnish labor, services, or materials, and in any event before the owner disburses final payment after receiving the contractor's final payment affidavit. Failure to serve the notice, or to serve it on time, is a complete defense to enforcement of a lien by any person. The notice itself is not a lien, cloud, or encumbrance on the property. [us-018]
Under section 713.06(3)(d), Florida Statutes, when final payment under a direct contract becomes due, the contractor must give the owner a final payment affidavit stating that all lienors who timely served a notice to owner have been paid in full, or listing each unpaid lienor and the amount due. The contractor must execute and deliver the affidavit at least 5 days before filing an action to enforce its lien, even if the contract was terminated before completion. If the affidavit lists outstanding bills, the owner may, after giving the contractor at least 10 days' written notice, pay those bills directly and deduct the amounts from the balance due the contractor. The statute provides the affidavit form, titled Contractor's Final Payment Affidavit. [us-019]
Under section 713.08(5), Florida Statutes, a claim of lien may be recorded at any time during the work or afterward, but not later than 90 days after the lienor's final furnishing of labor, services, or materials. If the original contract is terminated under s. 713.07(4), a claim of lien may not be recorded after 90 days following termination or 90 days after final furnishing, whichever occurs first. The claim of lien is recorded in the clerk's office of each county where the property is located. It must be served on the owner, and failure to serve it before recording or within 15 days after recording makes it voidable to the extent the failure prejudiced a person entitled to rely on service. [us-020]
Section 713.20(2), Florida Statutes, provides that a right to claim a lien may not be waived in advance, and a lien right may be waived only to the extent of labor, services, or materials already furnished. Any advance waiver is unenforceable. A lienor may waive, release, or satisfy any part of its lien at any time, either as to the amount due or as to work furnished through a certain date. The statute provides two forms, a Waiver and Release of Lien upon Progress Payment and a Waiver and Release of Lien upon Final Payment, and the progress payment form does not cover retention or work furnished after the stated date. [us-021]
Applied to your projectInvoice and Change Order Check, USD 149 →
General information about Florida rules, compiled from official sources. Not legal advice and not an inspection or engineering opinion; for your own case ask a Florida licensed attorney, engineer or the building department.