A second look at every pay application before the board signs.

Milestone inspections are turning into repair projects worth millions, paid by owners through special assessments. We check each pay application against the contract, the change orders and the previous payments, independent of the contractor, and give the board a written list of observations and questions. The decision to pay stays with the board and its engineer or architect of record.

Why boards need it

The repair wave is here, and the board carries the responsibility for every dollar.

Florida reformed condominium law after the Surfside collapse. Boards may no longer waive structural reserves, kickbacks to board members are a felony, conflicts of interest must be disclosed, and invoices belong to the records owners can inspect. Since July 2025, anyone bidding on a milestone inspection or reserve study must disclose whether they will also bid on the repairs. A board that pays an inflated application is exposed to its own owners.

903permit applications for repairs identified in phase two milestone inspections in 2024 and 2025.
$30Mupper end of the estimated repair values reported, with concrete, electrical and structural work most common.
1,575phase two milestone inspections completed in 2024 and 2025, each one a likely repair project.

Source: Florida OPPAGA, Report 26-04, Milestone Inspection Reporting Data 2024 and 2025, July 2026. Legal changes: Florida Statutes chapter 718 as amended through 2025; summary by Law Offices of Herb M. Milgrim, May 2026. Disclosure of follow-up bids: Florida HB 913 (2025), summary by Kovitz Shifrin Nesbit, 27 May 2025.

What we check

Six checks on every pay application.

01

The arithmetic

Every line of the continuation sheet recalculated, every total on the summary page traced back. Rounding is fine, a missing line is not.

02

The schedule of values

Scheduled values against the contract sum to date, lines billed above 100 %, and values that changed since the last application without a change order.

03

Change orders

Billing on change orders that are not signed, net change on the summary against the board's approved change order log, scope against the inspection report.

04

Front loading

Mobilization, general conditions, bonds and fees billed far ahead of the actual progress of the work.

05

Retainage and stored materials

Retainage at the contract rate, materials paid before installation only with invoices, insurance and a storage location.

06

The previous payment

What the contractor shows as previously billed against what the board actually certified last month.

Every finding names the line, the amount and the question to ask the contractor.

How it works

One cycle per application, before the board meeting.

WhenStepWho
Day 0Contractor submits the pay applicationContractor to the association or its manager
Day 1Application, contract, change order log and last certificate forwarded to usCommunity association manager
Days 1 to 3Review of all six checks, questions to the contractor collectedAlpha Quadrat
Day 3Written report: observations, questions and the amount in questionAlpha Quadrat to the board
Board meetingDecision on the payment, report filed with the official recordsBoard
3 business daysfrom complete documents to the written report.
1 fixed feeper application or one price for the whole project, agreed in writing.
7 languagesEnglish, Spanish, Portuguese, German, Italian, French or Dutch.
Sample report · Fictitious data

Pay application no. 4: $81,000 in question, five points to clarify before payment.

SeverityFindingAmount
HighNet change by change orders stated as $128,500; approved change orders add up to $86,500. CO-2 is not signed.$42,000
HighItem 8 bills $21,000 on change order CO-2, which is not approved.$21,000
HighPrevious certificates shown as $600,300; the board certified $582,300 last month.$18,000
MediumMobilization and general conditions billed at 100 % while the job is 45 % complete.$98,204
Low$48,000 of railings stored off site. Ask for invoices, insurance and storage location.$48,000

Concrete restoration of a fictitious 1980s condo tower, contract $2.4 million. You can run the same sample yourself in our free online check: alpha-quadrat.com/tools/pay-application-check

Scope and contact

Independent, document based, paid only by the association.

01

What we do

We review pay applications, change orders and payment history from the owner's side and give the board clear observations and questions with the amounts involved. The decision to pay stays with the board. We take no fees from contractors, suppliers or managers.

02

What we do not do

We do not inspect structures, certify quantities on site or give legal advice. Structural questions stay with the engineer of record, legal questions with the association's attorney.

03

Who we are

Alpha Quadrat is a building planning and project management firm from Wuppertal, Germany. Checking construction invoices and change orders is what our own tools were built for.

04

Fee and contact

Fixed fee per application or per project, confirmed in writing before we start. info@alpha-quadrat.com

Product sheet (PDF)

EnglishDeutschEspañolPortuguêsItalianoFrançaisNederlands
Prices

Start free, pay only for a person's work.

Free

AI document scan

$0

Upload a milestone inspection report, reserve study, budget, minutes or pay application as PDF. In a minute you see the figures that matter, warning signs and the questions to ask.

Scan a document
30 min

Video consultation, 30 minutes

$250

Book a 30 minute video consultation. We go through your documents with you; the fee is credited if you order a Condo Check or Restoration Cost Check afterwards.

For buyers

Condo Check

$695

Per unit. We read inspection reports, reserve study, budget, minutes and repair contracts and send a written cost outlook with the questions to ask within your review period.

For boards

Restoration Cost Check

$1,250

Per pay application, up to 150 line items. Checked against contract, change orders and previous payments, with observations and questions for the board within three business days.