1. Condo Check: unit 1204, fictitious tower, 1979
Purchase price $685,000, share of common expenses 0.85 %, monthly fee $1,240 rising 8 % a year. SIRS recommends $6.2 million structural reserve, $2.4 million on hand. Phase two milestone repairs of $3.8 million not yet funded, half planned with a bank loan. Special assessment of $14,800 already approved.
| Five-year cost for this unit | Amount |
|---|---|
| Fees and approved assessment | $102,095 |
| Possible further assessments (reserve gap and cash part of repairs) | $48,450 |
| Share of the association loan, repaid through fees | $16,150 |
| Total estimate | $166,695 |
| Year | Monthly fee | Fees that year |
|---|---|---|
| Year 1 | $1,240 | $14,880 |
| Year 2 | $1,339 | $16,070 |
| Year 3 | $1,446 | $17,356 |
| Year 4 | $1,562 | $18,745 |
| Year 5 | $1,687 | $20,244 |
Warning signs and questions
- High: structural reserve about 39 % funded. Ask how the association will close the gap; a special assessment or loan is likely.
- High: assessments and your share of unfunded items come to about 12 % of the purchase price, on top of the regular fees.
- Medium: part of the repairs is planned with a loan. Ask for the loan terms.
- Low: the approved $14,800 assessment: agree in the contract whether buyer or seller pays each installment.
2. Restoration Cost Check: pay application no. 4
Fictitious concrete restoration, contract $2.4 million, contract sum to date $2,528,500. Result: resolve these points before payment, $81,000 in question.
| Severity | Area | Item | Finding | Amount |
|---|---|---|---|---|
| High | Change orders | Net change by change orders stated as $128,500, approved change orders add up to $86,500. | $42,000 | |
| High | Change orders | 8 | Billing $21,000 on change order CO-2, which is not approved. | $21,000 |
| High | Previous application | Previous certificates shown as $600,300; the board certified $582,300 last month. | $18,000 | |
| Medium | Front loading | 1 | Mobilization and general conditions 100 % complete while the job is 45.4 %. Ask how this line is earned. | $98,204 |
| Low | Stored materials | 5 | $48,000 of railings stored off site. Ask for invoices, insurance and storage location. | $48,000 |
Run the same example yourself in the free Pay Application Check with "Load a sample".
Sources
- Calculation: Alpha Quadrat Condo Cost Outlook, fictitious inputs
- Calculation: Alpha Quadrat Pay Application Check, built-in sample
As of October 2026. General information, not legal, engineering or accounting advice. Alpha Quadrat reviews documents and estimates costs; it does not inspect buildings or practice law.
Related: Buyer's 7-day guide · Reading a SIRS · Special assessments · Pay application review · Bidding rules